ESTIMATE COST FOR LEARNING CENTER RESOURCE BLOCK
Hun Sen Chhouk U.S.S, Kampot Province
Level  :   + 1.00 m
No Description of works  Unit   Quantity   Unit Cost US$   Total 
1 Demolition and Site preparation
1-1 Sign Board for Resource  Upper Secondary School Lumpsum                  1.00            200.00                    200.00
1-2 Demolish existing  building, tries, fance, and other necessaries item for site security and site preparation Lumpsum                  1.00         2,000.00                 2,000.00
1-4 Notice Board for the project (40cm x 60cm) Lumpsum                  1.00            200.00                    200.00
Sub-Total (1)          2,400.00
2 Excavation, Backfill
2-1 Excavation for foundation and ground floor beams  Cu.m               236.50                 4.00                    946.00
2-2 Excavation for ground  beams(142mx0.45x0.3)  Cu.m                 19.70                 3.00                      59.10
2-3 Excavation for Septic tanks, 6 m3 capacity  Cu.m                 50.00                 3.00                    150.00
2-4 Backfilled Soil and compacting for Foundation  Cu.m               208.50                 3.00                    625.50
2-5 Soil backfilled for ground slab  Cu.m               627.00                 4.00                 2,508.00
Sub-Total (2)          4,288.60
3 Concrete Works
3-1 Substructure & Foundations
3-1-1 Stone Bedding under Pile Capping  , 100mm thick (Stone size 4x6)  Cu.m                 18.00              30.00                    540.00
3-1-2 Concrete piling, size 300 mm x 300 mm m            1,116.00              24.00              26,784.00
3-1-3 Stone Bedding under G. Floor beams, Gb (Stone size 4x6)  Cu.m                 14.50              30.00                    435.00
3-1-4 Stone Bedding under Septic tank, 150mm thick (Stone size 4x6)  Cu.m                   3.20              30.00                      96.00
3-1-5 Stone Bedding under Paving Concrete, 100mm thick (Stone size 4x6)  Cu.m                 12.30              30.00                    369.00
3-1-6 Stone Bedding under Slab (Stone size 4x6), 100mm thick  Cu.m                 54.00              30.00                 1,620.00
3-1-7 Lean Concrete under Slab, 30mm thick  Cu.m                 18.00              60.00                 1,080.00
3-1-8 Lean Concrete under G. Floor beams, Gbo, 30mm thick  Cu.m                   1.00              60.00                      60.00
3-1-9 Lean Concrete under Septic tank, 30mm thick  Cu.m                   0.61              60.00                      36.60
3-1-10 Lean Concrete under Paving concrete, 30mm thick  Cu.m                   3.70              60.00                    222.00
3-1-11 Lean Concrete Under  Pile Capping,30mm thick Cu.m                  5.50              60.00                    330.00
3-1-12 R.C Footings  capping  Cu.m                 55.50            250.00              13,875.00
3-1-13 R.C Short Column  Cu.m                   7.30            330.00                 2,409.00
3-1-14 R.C Staircase and entrance steps  Cu.m                   8.00            250.00                 2,000.00
Sub-Total (3-1)        49,856.60
3-2 Ground Floor
3-2-1 Concrete for Ground Floor Beams and Slab
3-2-2 R.C Septic tank (beams, bottoms and covers )  Cu.m                   2.35            180.00                    423.00
3-2-3 R.Concrete GB (level -0m)  Cu.m                 30.44            300.00                 9,132.00
3-2-4 R.Concrete ground floor slabs,WC celling  and R.C Slopping floor slab 60mm thickness  Cu.m                 42.00            180.00                 7,560.00
3-2-5 R.C Columns at the ground floor level  Cu.m                 15.50            300.00                 4,650.00
Sub-Total (3-2)        21,765.00
3-3 First Floor 
3-3-1 Concrete First floor 
3-3-2 R. Concrete Floor beams FB (250x550mm)  Cu.m                   6.60            300.00                 1,980.00
3-3-3 R. Concrete Floor beams FB (200x350mm)  Cu.m                 23.69            300.00                 7,107.00
3-3-4 R. Concrete Floor beams FB (200x550mm)  Cu.m                   3.96            300.00                 1,188.00
3-3-5 R.Concrete First slab, 100mm thick (level + 4.0m) and WC Celling  Cu.m                 51.17            220.00              11,257.40
3-3-6 Lintels, Sill beams under above Windows, doors Beam supporting Ventilation-200x200mm  Cu.m                   9.36            200.00                 1,872.00
3-3-7 Lintels, Sill beams under above Windows, doors Beam supporting Ventilation-200x100mm  Cu.m                   1.76            200.00                    352.00
3-3-8 R.C Columns at the above first Floor Slab  Cu.m                   9.64            300.00                 2,892.00
Sub-Total (3-3)        26,648.40
4 Roof structure 
4-1 Concrete structure
4-1-1 R. Concrete Roof Floor,60mm thick    Cu.m                 32.00            220.00                 7,040.00
4-1-2 R. Concrete Roof  Floor ,100mm thick   2000x32x100mm    Cu.m                   6.40            220.00                 1,408.00
4-1-3 R. Concrete Over beams  RB-(200x500mm )   Cu.m                 21.08            300.00                 6,324.00
4-1-4 R. Concrete Over beams  RB-(200x300mm )   Cu.m                   8.46            300.00                 2,538.00
4-1-5 R. Concrete Roof beams  RB-(200x250mm )x7000 x2   Cu.m                   0.70            250.00                    175.00
4-1-6 R. Concrete Roof beams  RB-(200x250mm)x8500x2  Cu.m                   0.43            250.00                    107.50
4-1-7 R. Concrete Roof beams  RB-(200x250mm)x41mx2  Cu.m                   4.10            250.00                 1,025.00
4-1-8 R. Concrete Roof beams  RB-(200x250mm)x12m  Cu.m                   0.60            250.00                    150.00
4-1-9 R. Concrete Roof beams  RB-(200x250mm)x25mx3  Cu.m                   3.75            250.00                    937.50
4-1-10 R.C Kingpost Columns   Cu.m                   3.61            250.00                    902.50
Sub-Total (4-1)        20,607.50
4-2 Steel structure
4-2-1 Steel Battens for roof with red oxide against  Corrosion &  Oil Painting and CPAC Rafters or equivalent  Sq.m               796.80              15.00              11,952.00
Sub-Total (4-2)        11,952.00
4-3  Roof tiles 
4-3-1 Roof tiles, first quality   CPAC   Sq.m               796.80                 8.50                 6,772.80
4-3-2 R.Concrete to cover  of  roof m              125.00                 5.00                    625.00
4-2-5 R.concrete gutter of  roof Cu.m                14.00            220.00                 3,080.00
4-2-6 Decoration roof gutter m              142.00              10.00                 1,420.00
4-2-7 Decoration of Khmer style Lumpsum                  5.00              25.00                    125.00
Sub-Total (4-3)        12,022.80
5 Masonry Work
5-1 Retaining Wall  ( Solid Bricks  20 Cm)  Sq.m               150.00              18.00                 2,700.00
5-2 Wall  Cladding Hollow Bricks   20 Cm   Sq.m               984.62              12.00              11,815.44
5-3 Wall  Cladding Hollow Bricks  10 Cm  Sq.m               472.84                 6.00                 2,837.04
5-4 Ventilation Louver Block (z) Sq.m              115.16              18.00                 2,072.88
5-5 Ventilation Louver Block  Sq.m                30.80                 8.00                    246.40
5-6 Sun shade Cu.m                  2.68            180.00                    482.40
Sub-Total (5)        20,154.16
6 Water proofing and down spouts 
6-1 Waterproofing at toilet block and sub-floor above entrance , (Flan coats), 2coats  Sq.m                 35.00                 4.00                    140.00
6-2 Galvanized down spouts, Ø 10 cm Lumpsum                  9.00                 8.00                      72.00
6-3 PVC down spouts Ø 114 mm m              124.00                 2.50                    310.00
Sub-Total (6)             522.00
7 Steel Doors, Windows and Steel Hand Rails
7-1 Steel and aluminum Doors 
7-1-1 Steel Doors with glass panel,  (1600 mm  x 2200 mm) included necessaries door's hardware and Decoration Frame  Set  10            230.00                 2,300.00
7-1-2 Steel Doors with glass panel,  (2900 mm  x 2500 mm) included necessaries door's hardware and Decoration Frame  Set                   2.00            500.00                 1,000.00
7-1-3 Steel Doors with glass panel,  (900 x 2200 mm) included necessaries door's hardware   and Decoration Frame  Set                   8.00            150.00                 1,200.00
Sub-Total (7-1)          4,500.00
7-2 Aluminum Windows and Curtain rails
7-2-1 Aluminum windows, glass panels with steel grill, W ( 1300 mm x 1600mm ) and Decoration Frame  Set                 28.00            114.00                 3,192.00
7-2-2 Aluminum windows, glass panels with steel grill, W (1300mm x 2800mm )and Decoration Frame  Set                   2.00            200.00                    400.00
7-2-3 Curtain rail and material for windows  ,W (1300mm x 1600mm) Set                28.00              10.00                    280.00
7-2-4 Curtain rail and material for windows  ,W (1300mm x 2800mm) Set                  2.00              12.00                      24.00
7-2-5 Sliding Door or Steel Doors with glass panel,  (1600 mm  x 2200 mm) included necessaries  Set                  2.00            230.00                    460.00
Sub-Total (7-2)          4,356.00
7-3 Glass panel with aluminum frame
7-3-1 White Glass panel with aluminum frame    Sq.m                 30.00              25.00                    750.00
Sub-Total (7-3)             750.00
7-4 Steel Hand Rails at Staircase and Veranda
7-4-1 Steel hand rails,  With Red oxide against Corrosion &  Oil Painting in Veranda m                22.50              25.00                    562.50
7-4-2 Steel hand rails, steel plate 60 x 6mm thick and good quality timber on tops (With Red oxide against Corrosion &  Oil Painting, timber with varnish) in Staircase m                33.60              30.00                 1,008.00
7-4-3 Steel door including locks for cheking Water Tank Piece                  1.00            250.00                    250.00
Sub-Total (7-4)          1,820.50
8 Finishing 
8-1 Plastering 
8-1-1 Cement Plastering for the walls  Sq.m           2,986.52                 3.00                 8,959.56
8-1-2 Cement Plastering for the ceiling  Sq.m           1,354.88                 3.00                 4,064.64
8-1-3 Cement plastering for retaining walls & Decoration Rim Sq.m              144.00                 4.00                    576.00
Sub-Total (8-1)        13,600.20
8-2 Ceramic floor tiles
8-2-1 Special Glass floor tiles for  entrance  (with patterns color)  Sq.m                   8.00              15.00                    120.00
8-2-2 Ceramic floor tiles, 50 x 50 cm, regular quality   Sq.m           1,099.70                 8.00                 8,797.60
8-2-3 Ceramic skirting floor tiles, 15 x 40 cm, regular quality m              512.58                 4.00                 2,050.32
8-2-4 Terrazzo for staircase and entrance steps (with patterns color)  Sq.m               136.00                 5.50                    748.00
8-2-5 Concrete Pavement around Building and main entrance step, 100mm thick  Cu.m                   7.00            110.00                    770.00
Sub-Total (8-2)        12,485.92
8-3 Painting
8-3-1 Oil painting  steel grill  for windows and doors  Sq.m               125.00                 6.00                    750.00
8-3-2 Oil painting for hand rails and staircase grills  Sq.m                 26.54                 6.00                    159.24
8-3-3 Primer coat for masonry walls  Sq.m           4,341.40                 1.70                 7,380.38
8-3-4 Emulsion paint use internal and external walls and ceilings , two coats with good quality paints   Sq.m           4,341.40                 2.00                 8,682.80
Sub-Total (8-3)        16,972.42
TOTAL1 (Civil Work)      224,702.10
9 Toilet blocks and drainage systems
9-1 Timber Doors with varnish & necessaries hardwire, DB (700 mm  x 2000mm)  Set                   8.00            150.00                 1,200.00
9-2 Timber Doors with varnish & necessaries hardwire, DB (700 mm  x 1200mm)  Set                   4.00              50.00                    200.00
9-3 Non-slip ceramic floor tiles in toilet blocks  Sq.m                 35.00              10.00                    350.00
9-4 Ceramic wall tiles, 2.5 m high  Sq.m               169.00              10.00                 1,690.00
9-5 Vitreous  flashing pans KARAT or equivalence  Unit                   8.00            150.00                 1,200.00
9-6 Vitreous  wash basins with tape marbles & mirror  Unit                   5.00              80.00                    400.00
9-7 Floor trap  Unit                 12.00                 5.00                      60.00
9-8 Stainless steel water tank, 2000 L, horizontal position, with steel support and automatic plotting  Unit                   2.00            350.00                    700.00
9-9 Septic tank, with 6 Cu.m capacity  Unit                   2.00         1,500.00                 3,000.00
9-10 Main hole  Unit                 10.00              80.00                    800.00
9-11 Water supply system  to toilet block (PVC pipes including other necessary work) Lumpsum                  4.00            400.00                 1,600.00
9-12 Water disposal from toilet to septic tank (PVC pipes including other necessary work) Lumpsum                  4.00            300.00                 1,200.00
9-13 False ceiling to cover,  disposal lines system  Sq.m                 80.00              15.00                 1,200.00
9-14 Water disposal from septic tank to City drainage system Ø350mm  m               120.00              15.00                 1,800.00
TOTAL 2 (Toilet) (9)        15,400.00
10 Science and computer lab
10-1 Solid brick for wall with thickness 10 cm Sq.m 50.85              10.00                    508.50
10-2 Reinforcement concrete slab (table) with thickness 8cm Cu.m 4.53            200.00                    906.00
10-3 Plastering brick wall internal and external Sq.m 102                 2.50                    255.00
10-4 Plastering on concrete slab  Sq.m 51.58                 2.50                    128.95
10-5 Epoxy 3mm thickness cover on reinforcement concrete slab (table) as shown in the technical drawings Sq.m 67.38            120.00                 8,085.60
10-6 Black plastic sing including other ancillary accessories  (need to see the sample before install ) Set 7            350.00                 2,450.00
10-7 Planel board including hinge glass as shown in the technical drawings Lumpsum 1            150.00                    150.00
10-8 Socket Set 36                 3.00                    108.00
10-9 Supply and install electrical cable 2x2.5mm² Cu/Cover (KTC or Equivalence) Lumpsum 1            100.00                    100.00
10-10 White door glass with alimium frame, support including key as shown in the technical drawings Sq.m 33.95              25.00                    848.75
10-11 Glass drawer ( including  Steel support 0.3-0.4m ) Set 38              15.00                    570.00
10-12 Painting internal external of walls and tables  Sq.m 153.58                 2.50                    383.95
10-13 Waste water drainage system including septic tank as shown in the technical drawings (PVC110 ; 8.5 ) Lumpsum 1            600.00                    600.00
10-14 Cold water system including installation Lumpsum 1            500.00                    500.00
10-15 Wooden chair with good quality including varnish painting as shown in the technical drawings Set 60              30.00                 1,800.00
10-16 White board Set 2              45.00                      90.00
10-17 Chemical clearing tank with accessories including installation Set 1            750.00                    750.00
10-18 Man hole Lumpsum 2            100.00                    200.00
TOTAL 3 (Science  &Computer Lab) (10)        18,434.75
11 Electrical works
11-1 EDC power connection fee (Tree Phase) Lumpsum                  1.00         1,000.00                 1,000.00
11-2 Main Board 28 lines  (Tree Phase)  Piece                  1.00              80.00                      80.00
11-3 Main Board (0.4 x 0.6m) Piece                  2.00              60.00                    120.00
11-4 Cable 1 x 1.5mm2  Lot                 42.00              25.00                 1,050.00
11-5 Cable 1 x 2.5mm2  Lot                 29.00              30.00                    870.00
11-6 Cable 1 x 4mm2  Lot                   2.00              35.00                      70.00
11-7 Cable 1 x 16mm2  Lot                   2.40              40.00                      96.00
11-8 Cable 4 x 35mm2  m                 50.00              22.00                 1,100.00
11-9 Cable 4 x 50mm2    including Steel Pole  m               200.00              30.00                 6,000.00
11-10 Cable Audio  Lot                   2.00            100.00                    200.00
11-11 Flexible Num.20  Lot                 34.00                 5.00                    170.00
11-12 Flexible Num.25  Lot                 28.00                 7.00                    196.00
11-13 Flexible Num.34  Lot                   6.00              10.00                      60.00
11-14 PVC no.5 m                48.00                 2.00                      96.00
11-15 Circuit Breaker 4P 100A  Set                   1.00            100.00                    100.00
11-16 Circuit Breaker 4P 63A  Set                   4.00              80.00                    320.00
11-17 Circuit Breaker 4P 250  Set                   1.00              70.00                      70.00
11-18 Circuit Breaker 4P 10A  Set                 27.00              20.00                    540.00
11-19 Circuit Breaker 4P 15A  Set                 10.00              23.00                    230.00
11-20 Circuit Breaker 4P 20A  Set                 90.00              15.00                 1,350.00
11-21 Double Fluorescent 1.2m in ceiling  Set                 65.00              30.00                 1,950.00
11-22 Single Fluorescent 1.2m in ceiling  Set                   6.00              20.00                    120.00
11-23 Single Fluorescent 0.6m in ceiling  Set                   6.00              15.00                      90.00
11-24 Circuit Breaker Box for each room  Set                 18.00              12.00                    216.00
11-25 Fluorescent Disc 1.2 m  Set                 16.00              15.00                    240.00
11-26 Speaker 400w With Support  Set                   6.00              20.00                    120.00
11-27 Socket  Set                 65.00                 3.50                    227.50
11-28 Switch 1 way 1 pole  Set                 24.00                 4.00                      96.00
11-29 Switch 1 way 2 pole  Set                 15.00                 6.00                      90.00
11-30 Switch 1 way 3 pole  Set                   4.00                 7.00                      28.00
11-31 Switch 1 way 4 pole  Set                   4.00                 8.00                      32.00
11-32 Switch 1 way 5 pole  Set                   9.00              10.00                      90.00
11-33 Switch 2 way 1 pole  Set                 12.00                 8.00                      96.00
11-34 Switch 2 way 2 pole  Set                   4.00                 8.00                      32.00
11-35 Demer Switch  Set                 12.00              15.00                    180.00
11-36 Exhaust Fans  Set                 15.00              15.00                    225.00
11-37 Ceiling Fans  Set                 30.00              50.00                 1,500.00
11-38 Wall Fans  Set                   8.00              30.00                    240.00
11-39 Wall split Air condition 24000 BTU in meeting room , (Panasonic or equivalent)  Set                   4.00            800.00                 3,200.00
11-40 Wall split Air condition 24000 BTU in meeting room , (Panasonic or equivalent)  Set                   4.00            800.00                 3,200.00
11-41  Amplifier 300W(Power out put), 2 microphones with Support and DVD player &Cable Audio including installation Lumpsum 1            800.00                    800.00
11-42 Earthling System Lumpsum                  1.00         1,500.00                 1,500.00
TOTAL 4 (Electrical) (11)        27,990.50
Grand total      286,527.35